image - Shooters Hill Wind Farm Construction
image - Shooters Hill Wind Farm Construction

Shooters Bottom, Somerset - groundwork complete

12th December

The foundation is now complete. Everything has been backfilled and the site looks neat and tidy - ready to start grid works after Christmas.

The turbine's not coming until early Spring. We don't have a definite date yet but watch this space for updates.

The proposed wind turbine will generate up to nearly 7 million units of green electricity each year. The turbine, which will be sited near Chewton Mendip in Somerset, will provide electricity for up to 2,000 local homes, which is around 5% of all homes in Mendip District.

<< Back

Vital Statistics

Shooters Bottom , Somerset

Site address -
Shooters Bottom Farm, Chewton Mendip, Somerset

Status - APPROVED

Turbines - 1

Capacity - 2MW

Generation kWh - up to 6.7million

Equivalent homes - up to 2,031 

Rotor diameter - up to 70m

Hub height: up to 67m

Carbon dioxide (CO2)
savings - up to 6,751 tonnes

Sulphur dioxide (SO2)
savings- up to 102 tonnes

Nitrogen oxide (NOX)
savings - up to 28 tonnes

Download the pdf factsheet here